Originally Posted by
Devin_82
If I am understanding your question, a workflow that has worked for me in the past is to do the following:
1. Open up a blank file and create an Area Scheme (I'm thinking this is what you meant by area TYPE?) with a name that exactly matches (including letter case) the name of the scheme for the original schedule.
2. Copy the schedule from the original project to the new project.
3. Rename the Area Scheme in the new project to exactly match the name of the second scheme you are trying to get the schedule to recognize.
4. Rename the schedule.
5. Copy the renamed schedule from the new project back into the original project and you should now see the data from the second Area Scheme.
I know this seems like a lot of steps for a single schedule, but imagine you have a whole series of schedules that need to be translated, recreating them will take forever, especially if they have a bunch of calculated values. Hope this helps.