I work at an MEP firm, and would like to get more insight on how exactly this workflow method is initially setup and updated when architectural changes come in. I know this is called the "Master Model" setup in some firms. The steps as I understand it in theory are as follows:
1. You have one "master" architectural model, that you initially clean up, purge, adjust specific views as needed, which then ultimately gets linked into each MEP trade's separate models.
2. You create 4-5 separate models, one for each MEP trade (M, E, P, FP, T)
3. In each separate MEP model, you link in the "master" architectural model from step 1, and simply use "Linked View" settings for each MEP view since you're controlling the architectural background elements in the "master" arch model only.
4. Any updates from the architect, just get cleaned up, purged, etc, and saved over the "master" model from step 1, which in turn updates each of the separate MEP models view backgrounds as well.
Am I explaining this correctly? Is there any other things I should know about this method, tips, tricks, or pitfalls that I should be aware of? Also is this the preferred method of setting up multi-trade models?
Thanks in advance