    How do i get the index to read out of order. And also add my consultants. For instance:

    G0.1
    A2.1
    etc.

  2. #2
    Certified AUGI Addict patricks's Avatar
    Join Date
    2004-06
    Location
    Memphis TN area
    Posts
    7,048
    Login to Give a bone
    1

    Default Re: Sheet Index Question

    You need to add a parameter to your sheets, something like a simple integer field, and then set your G sheets to 1 (for example), A sheets to 2, etc. and then have that field hidden in your sheet index, and sort the index by that hidden field first, and then by sheet number second.

  3. #3
    I could stop if I wanted to
    Join Date
    2007-07
    Location
    London, UK
    Posts
    361
    Login to Give a bone
    0

    Default Re: Sheet Index Question

    You can create another sheet parameter and sort the schedule by it first (then sheet number).
    G -> 0 ; A -> 1 ; etc etc...
    Make sure it does not appear in the schedule (make it a hidden field).

  4. #4
    I could stop if I wanted to
    Join Date
    2007-07
    Location
    London, UK
    Posts
    361
    Login to Give a bone
    0

    Default Re: Sheet Index Question

    AH AH AH
    missed patricks for 1 minute!

  5. #5
    Certified AUGI Addict patricks's Avatar
    Join Date
    2004-06
    Location
    Memphis TN area
    Posts
    7,048
    Login to Give a bone
    0

    Default Re: Sheet Index Question

    type fastah, young grasshoppah!!

  6. #6
    Active Member
    Join Date
    2005-11
    Posts
    53
    Login to Give a bone
    0

    Default Re: Sheet Index Question

    Thanks guys that did it.

  7. #7
    AUGI Addict DaveP's Avatar
    Join Date
    2002-12
    Location
    St Paul, MN
    Posts
    1,569
    Login to Give a bone
    0

    Default Re: Sheet Index Question

    I'd recommend numbering those parameters you add 100, 200, 300, etc. instead of 1, 2, 3 ...
    If you use 1, 2, 3 ... and your consultant adds another out-of order sheet, you're stuck. If you use the hundreds, you've got flexibility in between.

    Maybe its just from my days programming in old GW basic when you had to number every line....

Similar Threads

  1. Sheet Index with sheet number scheduled twice
    By lboylan in forum Revit Architecture - General
    Replies: 3
    Last Post: 2011-10-14, 07:26 PM
  2. Sheet Index Question Re: Placeholders
    By dgreen.49364 in forum Revit Architecture - General
    Replies: 3
    Last Post: 2010-11-08, 09:45 PM
  3. Sheet Index
    By bruckmandesign in forum Revit Architecture - General
    Replies: 26
    Last Post: 2009-01-08, 04:59 PM
  4. Replies: 3
    Last Post: 2006-04-26, 02:35 PM
  5. SHEET INDEX
    By jprzybylski in forum AutoCAD Sheet Set Manager
    Replies: 2
    Last Post: 2005-04-14, 01:58 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •