    Anyone have a good suggestion as to how to do alternate bids. We're working on a new school and basically have two double loaded classroom 'wings', and each wing has an alternate to add two more classrooms on the end of them. I'm not too sure as the best way to go about doing this. Which is the better method....Design Options, Worksets, something else??? I don't have enough forsight to see which method is better in the long run. Thanks for any suggestions

  2. #2
    Certified AUGI Addict patricks's Avatar
    Join Date
    2004-06
    Location
    Memphis TN area
    Posts
    7,048
    Login to Give a bone
    0

    Default Re: Alternate Bids???

    I typically model them either on a separate workset, or another phase after my new construction phase. Then I show a separate "alternate plan" at the end of my architectural set, like on my A900 sheets.

    If the alternate is an either/or situation, then I might do it as a design option.

    For extra school classrooms, I would probably do it on a phase after your new construction phases with the rest of the building.

  3. #3
    Certifiable AUGI Addict twiceroadsfool's Avatar
    Join Date
    2006-01
    Location
    ---
    Posts
    4,516
    Login to Give a bone
    0

    Default Re: Alternate Bids???

    I would do it as a design option if its either/or; or a phase if it is a now and later issue. I dont go the workset route as ive (personally) found it leads to problems later...

  4. #4
    Certified AUGI Addict patricks's Avatar
    Join Date
    2004-06
    Location
    Memphis TN area
    Posts
    7,048
    Login to Give a bone
    0

    Default Re: Alternate Bids???

    We just previously completed a small building where a few rooms and their associated finishes and fixtures were bid out as an alternate (one whole end of the building was just a shell under base bid). Then we had another alternate for some millwork.

    I created that first alternate on a separate later phase, and then had my alternate plans on A900 with all of the base bid stuff shown as halftone (since it was all existing to remain on a previous phase).

    However for the millwork, since those were just objects in the room, I just created a separate workset for those few items, with that workset off by default.

    In the end it all was pretty clear and worked out well.

Similar Threads

  1. CR308-1: BIM Bids Only! How to Get Your Subcontractors to Bid an Autodesk Revit Project
    By Autodesk University in forum Construction and Real Estate
    Replies: 0
    Last Post: 2014-12-01, 01:05 AM
  2. Alternate Decimal Separator for Alternate Units in Dimensions
    By Wish List System in forum AutoCAD Wish List
    Replies: 2
    Last Post: 2013-08-28, 04:33 PM
  3. Alternate to Callout
    By buttonsrtoys in forum Revit Architecture - General
    Replies: 3
    Last Post: 2010-02-09, 11:27 PM
  4. Alternate Dim BELOW dimline
    By knoble in forum AutoCAD General
    Replies: 2
    Last Post: 2004-07-23, 04:31 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •